Aerial photo of a motorway junction

North America | Transport

I-77 Highway

The project entails the design, construction, finance, operation and maintenance of 26 miles of dynamic priced managed lanes running between Lake Norman and Charlotte, North Carolina.

The concession was granted by North Carolina DOT, with a term of 50 years, to I-77 Mobility Partners (a joint venture between the Company, Ferrovial and Aberdeen), construction commenced in November 2015 and was completed in November 2019.

The EPC contractor for the project is Sugar Creek Construction which is comprised of FA Southeast and English Construction. Kapsch TrafficCom has been appointed to provide the toll system and integration services. Cintra/Ferrovial manage the asset operation and are responsible for routine maintenance on both express and general purpose lanes.